1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage: System Integration & Test

Benchmark

7

8

8

8

8

8

8

55

Current Project

9

7

8

8

8

8

8

56

Explanation

Schedule: The project is progressing to schedule with the development and delivery of combat system baselines. Combat system baseline development is ahead of the installation schedule because of delays in the submarine docking program and the schedule assessment is linked to baseline development rather than the installation schedule.

Cost: Confidence in cost is lower than the benchmark because of potential cost effects of delay due to submarine availability affecting the installation program.