Description | Remedial Action |
There is a possibility that installation of the Replacement Combat System equipment will be affected by slippages in submarine availability leading to an impact on schedule. | This risk has now been realised and is addressed as an Issue in Section 4.2 Major Project Issues. |
There is a possibility that the Tactical Command Control system baseline will be affected by unforeseen US Navy led baseline changes leading to an impact on cost and schedule. | This risk is being treated by: ■ Exercising clauses within the Memorandum of Understanding that require the US Navy to consult with the Commonwealth of Australia. ■ Presenting technical architecture changes to the Executive Steering Committee for decision. ■ Establishing Project Authority positions in the Joint Project Office (US) to enable the RAN to influence prospective changes to the US program. ■ Monitoring and approving all system engineering changes through the Engineering Review Board. |