This section reports on major project risks and issues faced by the project. It also identifies those projects whose outcomes are necessary for the success of the project being reported on.

Section 4.1 Major Project Risks: DMO's project risk management methodology rates risks at four levels low, medium, high and extreme; this section reports on the two highest levels via "extreme" and "high" risks and describes the planned remediation measures for these risks.

Section 4.2 Major Project Issues: Project issues comprise major risks that have been realised or significant matters that have emerged during the execution of the project that require special management attention. This section lists these issues and describes proposed remediation action for these issues.