KEY ACTIONS AND RESPONSIBILITIES MATRIX: FORMALISING THE CONTRACT

This matrix shows a typical sequence of steps in finalising a contract, the key stakeholder groups involved and documents produced:

has responsibility for this step

involved in this step (for example, giving advice, being informed)

gives formal approval

Document is used

Documents are created or updated (see explanation of this table at the end of Part 2, p. 46)

__________________________________________________________

Action or step:

Senior Management / Minister

Senior manager

User groups

Negotiation team

Contract management team

Specialist advisers

Preferred contractor

Negotiating strategy

Risk plan

Probity plan

Financial plan

Contract

Announcement documentation

Review and update risks for this stage

Finalise probity plan and requirements

Ensure all parties are aware of probity requirements

Develop negotiating strategy

Undertake negotiations

Obtain final approval of the agreed contract

Obtain all necessary material approvals

Develop announcement and signing approach

Contract signing

Enter details in financial and contract system(s); arrange public reporting

Advise and debrief unsuccessful tenders

Announcement

Hand over of responsibility to contact management team

Complete and file all contract tendering, evaluation and decision documentation