Prime Contractor(s) | Scope Outline | Type (Price Basis) | Form of Contract | Signature |
AWD Alliance (ASC AWD Shipbuilder Pty Ltd and Raytheon Australia Pty Ltd) | 3 AWDs and support systems | Variable with Pain/Gain Share | Alliance | Oct 07 |
Navantia | Platform Design | Fixed with indices escalation | Alliance based | Oct 07 |
US Government | 3 Aegis Combat Systems | Oct 05 (1) |
Note (1): | The original FMS contract was signed as part of SEA 4000 Phase 1 for initial engineering services. Subsequent scope changes, including the acquisition of the Aegis Combat System, were transferred to SEA 4000 Phase 3 in July 2007. |