1.6  Project Maturity Score and Benchmarks

Maturity Score

Attributes

 

Schedule

Cost

Requirement

Technical Understanding

Technical 
Difficulty

Commercial

Operations and Support

Total

Project Stage: Critical design Review

BenchMark

7

7

7

8

7

7

7

50

Current Project

7

7

8

8

7

7

7

81

Explanation

Requirement score was increased to 8 following the successful completion of the support detailed Review in June