3.2 Contractor Test and Evaluation Progress

Test and Evaluation

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Integration

Ship 1 Complete Hull Integration(1)

Dec 12

Dec 12

Dec 12

0

 

Ship 1 Start Combat System Light Off(2)

Dec 13

Dec 13

Dec 13

0

 

Ship 2 Complete Hull Integration

Mar 14

Mar 14

Mar 14

0

 

Ship 2 Start Combat System Light Off

Mar 15

Mar 15

Mar 15

0

 

Ship 3 Complete Hull Integration

Jun 15

Jun 15

Jun 15

0

 

Ship 3 Start Combat System Light Off

Jun 16

Jun 16

Jun 16

0

Acceptance

Ship 1 - Commencement of Category 5 Trials

Aug 14

Aug 14

Aug 14

0

 

Ship 1 - Provisional Acceptance

Dec 14

Dec 14

Dec 14

0

 

Ship 2 - Commencement of Category 5 Trials

Nov 15

Nov 15

Nov 15

0

 

Ship 2 - Provisional Acceptance

Mar 16

Mar 16

Mar 16

0

 

Ship 3 - Commencement of Category 5 Trials

Feb 17

Feb 17

Feb 17

0

 

Ship 3 - Provisional Acceptance

Jun 17

Jun 17

Jun 17

0

Variance Explanations

Note(1):  Complete Hull Integration is achieved when the last erection joint is structurally inspected and accepted.

Note(2):  Start Combat System Light Off verifies the readiness of the first set of installed combat system equipment and authorises the commencement of CAT 4 testing.