3.4 Progress toward Final Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

FOC

Dec 18

Dec 18

0

N/A

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Jun 07

Jun 16

Dec 18