Description | Remedial Action |
The Program does not have an agreed Project Certification Plan and Certification Basis. The lack of an agreed Project Certification Plan and Certification Basis may have a significant impact on cost and schedule. | The Project Certification Plan has now been finalized and agreed with the RAN. This issue has been retired. |
The release of design information from the US Navy may not be sufficient to satisfy regulatory requirements. | The Program is working with the US Navy to ensure that the Program needs are understood and addressed within the bounds of release-ability issues. Mitigation plans are being developed to address the situations where information will not be released. |
Design changes are required to meet emerging requirements. | The Program is working through the three Star Project Management Steering Group to manage the introduction of change to the program and its impact on cost and schedule. |
The division of technical assistance required from the US Navy for the FMS case between the Alliance and the Program office needs definition. | A working agreement is in place between the Alliance and the Program office which addresses the use of technical assistance. |