Maturity Score | Attributes | Total | |||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | |||
Project Stage: System Integration and Test | Benchmark | 7 | 8 | 8 | 8 | 8 | 8 | 8 | 55 |
Current Project | 7 | 7 | 7 | 8 | 8 | 6 | 9 | 52 | |
Explanation | • Cost: While major risks in subsystem and integrated system performance remain to be retired, overall estimate at completion is forecast to be within current contingency. • Requirement: System Integration testing has yet to be completed. • Commercial: The Commonwealth assesses that, despite striking a revised schedule baseline under the Settlement Deed, there is continuing risk to Boeing's delivery plans. • Operations and Support: Operations and support systems have begun transitioning to the operational environment with Initial Acceptance of the first two aircraft. | ||||||||
Project Stage | Total Benchmark Score | Total Current Score | |
System Integration and Test | 55 | 52 | |
| |||