1.6  Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage:

System Integration and Test

Benchmark

7

8

8

8

8

8

8

55

Current Project

7

7

7

8

8

6

9

52

Explanation

•  Cost: While major risks in subsystem and integrated system performance remain to be retired, overall estimate at completion is forecast to be within current contingency.

  Requirement: System Integration testing has yet to be completed.

  Commercial: The Commonwealth assesses that, despite striking a revised schedule baseline under the Settlement Deed, there is continuing risk to Boeing's delivery plans.

•  Operations and Support: Operations and support systems have begun transitioning to the operational environment with Initial Acceptance of the first two aircraft.

 

Project Stage

Total Benchmark Score

Total Current Score

System Integration and Test

55

52

2008-09 DMO MPR Status - - - - -

2009-10 DMO MPR Status - - - - -