3.1  Design Review Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

Preliminary Design

Airborne Mission System

Jul 02

 

Jun 02

(1)

Operational Mission Simulator

Jan 03

 

Apr 03

3

Mission Support System

Mar 03

 

Apr 03

1

Operational Flight Trainer

Aug 03

 

Jul 03

(1)

Airborne early warning and control Support Facility

Nov 03

 

Oct 03

(1)

Critical Design

Airborne Mission System

Feb 03

 

Dec 02

(2)

Operational Mission Simulator

Nov 03

 

Nov 03

0

Mission Support System

Dec 03

 

Nov 03

(1)

Operational Flight Trainer

May 04

 

Apr 04

(1)

Airborne early warning and control Support Facility

Oct 04

 

Sep 04

(1)

Variance Explanations

Variances to Design Reviews were due to various minor causes.