Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | Airborne Mission System | Mar 06 | Jun 10 | Aug 10 | 54 |
Operational Mission Simulator | Mar 06 | Dec 10 | Jan 11 | 59 | |
Operational Flight Trainer | Dec 05 | Dec 05 | Dec 05 | 0 | |
Mission Support System | Jul 06 | Oct 08 | Jul 10 | 48 | |
AEW&C Support Facility | Dec 06 | Dec 10 | Jan 11 | 49 | |
Acceptance | Airborne Mission System | Nov 06 | Oct 10 | Mar 11 | 52 |
Operational Mission Simulator | May 06 | Mar 11 | Apr 11 | 59 | |
Operational Flight Trainer | Mar 06 | Nov 08 | Feb 09 | 35 | |
Mission Support System | Aug 06 | Sep 10 | Oct 10 | 50 | |
AEW&C Support Facility | Mar 07 | Mar 11 | Jul 11 | 52 | |
Variance Explanations | Operational Flight Trainer Acceptance Test and Evaluation - Disagreement between Boeing and Commonwealth over specification requirements. Mission Support System - System Integration Test and Evaluation, previously reported as completed in May 09, has been resumed as a result of deficiencies subsequently revealed during integrated mission testing. All other items - Problems associated with sub-system integration; mission computing, radar and electronic support measures maturity and stability; and supplier hardware availability. Note: The Current Planned dates reflect the revised schedule agreed as part of the Settlement Deed, whereas the Forecast dates and associated Variances reflect Defence's assessment of when completion is likely to be achieved. | ||||