Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
Test Readines Review | MRH aircraft - Phase 2 | Jul 06 | Nov 06 | Dec 06 | 5 |
MRH aircraft - Phase 4/6 | N/A | N/A |
| N/A | |
MRH Software Support Centre | N/A | Oct 08 | Nov 08 | 1 | |
Electronic Warfare Self Protection Support System | N/A | N/A | Nov 07 | N/A | |
Ground based Mission planning and Management System | N/A | N/A |
| N/A | |
MRH Instrumented System | Nov 08 | May 09 | Dec 09 | 13 | |
Full Flight and Mission Simulators | Jun 11 | Feb 12 | May 12 | 10 | |
Acceptance | Type Acceptance Review Special Flight Permit 1 | Oct 07 |
| Dec 07 | 2 |
Type Acceptance Review Special Flight Permit 2 | Jun 08 |
| Jun 08 | 0 | |
Extension Special Flight Permit 2 | Feb 09 |
| Feb 09 | 0 | |
Australian Military Type Certificate | Dec 08 | Dec 10 | Dec 10 | 24 | |
Full Flight and Mission Simulators | Mar 13 | Oct 13 | Jan 14 | 10 | |
Ground based Mission planning and Management System Lot 1 | Feb 09 | Sep 09 | Dec 09 | 10 | |
Ground based Mission planning and Management System Lot 2 | Feb 09 | Dec 09 | Apr 10 | 14 | |
MRH Software Support Centre | Feb 09 | Feb 09 | Dec 08 | (2) | |
Electronic Warfare Self Protection Support System | Dec 07 | Dec 07 | Dec 07 | 0 | |
MRH Instrumented System | Mar 10 | Jun 10 | Jul 10 | 4 | |
Aircraft Acceptance | MRH aircraft #01 (First aircraft) | Dec 07 |
| Dec 07 | 0 |
MRH aircraft #05 (First Australian built aircraft) | Dec 08 |
| Dec 08 | 0 | |
MRH aircraft #11 (Most recent) | Nov 09 | Dec 09 | Mar 10 | 4 | |
MRH aircraft #12 (Next aircraft) | Dec 09 | Feb 10 | Jul 10 | 7 | |
MRH aircraft #46 (Final aircraft) | Jul 14 | Jul 14 | Jul 14 | 0 | |
Variance Explanations | The first Airworthiness Board (for a Special Flight Permit) was conducted in November 2007 and granted in December 2007. Achievement of the Australian Military Type Certificate has proved problematic due to insufficient levels of Rate of Effort. Rate of Effort is required to validate that in-service support arrangements for the fleet are sufficient to cope with current numbers of aircraft and are growing in maturity to meet fleet requirements. Further, the numbers of trained aircrew have been limited by the low Rate of Effort and are a criterion for Australian Military Type Certificate. Operating under the Special Flight Permit rather than an Australian Military Type Certificate has not caused any project delay to date. Acceptance of aircraft broadly remains on schedule, although some aircraft have been accepted several months behind schedule. Acceptance of MRH#11 was delayed due to: delays to previous aircraft, the 2009/2010 Christmas and New Year stand down periods, and the use of this aircraft to perform aeromedical equipment compatibility testing before acceptance. Acceptance activities on future aircraft (MRH#12) are currently pending resolution of an engine failure incident that occurred on an in-service aircraft on 20 April 2010. This is expected to be resolved in July 2010. MRH Instrumentation System. The 13 month delay to closure of Test Readiness Review was due to electronic compatibility test design issues not resolved until November 2009. This delay was mitigated by the development of an interim MRH Instrumentation System capability used for a test activity in October 2009. Delays experienced through the FFMS design phase have flowed into development and production activities. | ||||