4.2  Major Project Issues

Description

Remedial Action

The schedule to achieve Australian Military Type Certificate and Service Release in 2010 will be adversely affected due to the inability to generate the required aircraft rate of effort.

Resolve technical and spares issues that restrict aircraft availability. Streamline Commonwealth and Industry support processes to maximise available flight opportunities.

The schedule to achieve Australian Military Type Certificate and Service Release in 2010 will be adversely affected by failing to achieve a sufficiently mature MRH System.

Measure progress against capability Key Performance Indicators. Maximise opportunities to use certification processes of other NH90 nations. Maintain focus on achieving capability milestones and targets.

Insufficient breakdown spares to support MRH90 operations.

This issue has been retired

Interactive Electronic Technical Publications inadequate to support maintenance activities and flight operations.

This issue has been retired