3.4  Progress toward Final Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

FOC

Dec 12

Dec 12

0

N/A

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Mar 07

Dec 10

Dec 12