Contractor | Signature date | Price at signature (base) $m | Quantities at signature | Price at 30 Jun 10 (base) $m | Quantities at Jun 10 | Equipment | Notes |
BAE Systems | Oct 07 | 2,268.1 | 2 | 2,271.2 | 2 | LHD ships and integrated support systems | 7 |
Major equipment received and quantities to 30 Jun 10 | |||||||
Detailed Design Review achieved. Construction of main hull sections underway. | |||||||
Notes | |||||||
Notes 1: | This project's original DMO budget amount is that prior to achieving Second Pass Government approval. | ||||||
Notes 2: | Administration savings harvest. | ||||||
Notes 3: | To fund a risk reduction activity for the Project to obtain design data and develop designs to meet Australian essential requirements. | ||||||
Notes 4: | First Pass approval. | ||||||
Notes 5: | Transfer of funding for technical studies from DSTO. | ||||||
Notes 6: | Other expenditure comprises: Operating Expenditure, Offer Definition, Consultants, Foreign Military Sales, Contractor Support and Minor Capital expenditure not attributable to the Prime contract. | ||||||
Notes 7: | Contract Price at Revision 17. | ||||||