Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | LHD Ships #1 and 2 | Mar 15 | Mar 15 | Mar 15 | 0 |
Acceptance | LHD Ship#1 Project Acceptance | Jan 14 | Jan 14 | Jan 14 | 0 |
LHD Ship#2 Project Acceptance | Aug 15 | Aug 15 | Aug 15 | 0 | |
LHD Final Acceptance | Sep 15 | Sep 15 | Sep 15 | 0 | |
Variance Explanations | N/A | ||||