2.4  In-year Budget Expenditure Variance

Estimate $m

Actual $m

Variance $m

Variance Factor

Explanation

 

 

 

FMS

Financial Year 2009-10 end of year expenditure achievement was less than the Additional Estimate plan due to a planned support contract mobilisation payment not required, the reschedule of the delivery of Integrated Logistic Support spares to later financial years, improved foreign exchange rates and the revised effective date of the Light Trailer acquisition contract.

 

Overseas Industry

(1.0)

Local Industry

 

Brought Forward

(0.6)

Cost Savings

 

FOREX Variation

(1.6)

Commonwealth Delays

34.0

30.8

(3.2)

Total Variance