3.2 Contractor Test and Evaluation Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

Test Readiness Review

LLC: Light Lightweight Contract (all except Surveilance & Reconnaissance and Carryall hardtop)

Oct 09

Dec 09

2

LLC: Light Lightweight Contract Truck, Light, Surveillance and Reconnaissance vehicle only

Aug 10

Apr 11

8

LLC: Light Lightweight Contract Truck, Lightweight, Carryall hard Top

Oct 09

Jul 10

9

LLC: Light Lightweight Contract Group 1 Modules

Jan 10

May 10

4

LLC: Light Lightweight Contract Group 2 Modules

Oct 10

Nov 11

13

LLC: Light Lightweight Contract Group 3 Modules

Jan 10

Nov 10

10

LLT: Light & Lightweight Trailers

Jul 11

Jul 11

0

Functional Configuration Audit

LLC: Light Lightweight Contract (all except Surveillance, Reconnaissance)

Aug 10

Sep 10

1

LLC: Light Lightweight Contract (Surveillance and Reconnaissance only)

Feb 11

Sep 11

7

LLC: Light Lightweight Contract Group 1 Modules (L-M-CCC; L-M-CDC; L-M-CANDC)

Jun 10

Jan 11

6

LLC: Light Lightweight Contract Group 2 Modules (L-V-SUR; L-M-AMB; L-M-PCRS)

Apr 11

Aug 11

4

LLC: Light Lightweight Contract Group 3 Modules (L-M-CPM; L-M-CP)

Aug 10

Jan 11

5

Acceptance Verification and Validation

LLT: Light & Lightweight Trailers

Jul-Oct 11

Jul-Oct 11

0

Variance Explanations

Test Readiness Reviews with a variance between the originally planned and achieved/forecast date is due to changes in system specifications by the Commonwealth.

There is no baseline established for MHC at this stage. The schedule will be negotiated from tenderers responses to the amended Stage 2 RFT. The duration and number of test and evaluation reviews will be determined by the level of MOTS compatability in the offered solutions. A schedule baseline will be established once contract negotiations have been conducted.