| Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
| Test Readiness Review | LLC: Light Lightweight Contract (all except Surveilance & Reconnaissance and Carryall hardtop) | Oct 09 |
| Dec 09 | 2 |
| LLC: Light Lightweight Contract Truck, Light, Surveillance and Reconnaissance vehicle only | Aug 10 |
| Apr 11 | 8 | |
| LLC: Light Lightweight Contract Truck, Lightweight, Carryall hard Top | Oct 09 |
| Jul 10 | 9 | |
| LLC: Light Lightweight Contract Group 1 Modules | Jan 10 |
| May 10 | 4 | |
| LLC: Light Lightweight Contract Group 2 Modules | Oct 10 |
| Nov 11 | 13 | |
| LLC: Light Lightweight Contract Group 3 Modules | Jan 10 |
| Nov 10 | 10 | |
| LLT: Light & Lightweight Trailers | Jul 11 |
| Jul 11 | 0 | |
| Functional Configuration Audit | LLC: Light Lightweight Contract (all except Surveillance, Reconnaissance) | Aug 10 |
| Sep 10 | 1 |
| LLC: Light Lightweight Contract (Surveillance and Reconnaissance only) | Feb 11 |
| Sep 11 | 7 | |
| LLC: Light Lightweight Contract Group 1 Modules (L-M-CCC; L-M-CDC; L-M-CANDC) | Jun 10 |
| Jan 11 | 6 | |
| LLC: Light Lightweight Contract Group 2 Modules (L-V-SUR; L-M-AMB; L-M-PCRS) | Apr 11 |
| Aug 11 | 4 | |
| LLC: Light Lightweight Contract Group 3 Modules (L-M-CPM; L-M-CP) | Aug 10 |
| Jan 11 | 5 | |
| Acceptance Verification and Validation | LLT: Light & Lightweight Trailers | Jul-Oct 11 |
| Jul-Oct 11 | 0 |
| Variance Explanations | Test Readiness Reviews with a variance between the originally planned and achieved/forecast date is due to changes in system specifications by the Commonwealth. There is no baseline established for MHC at this stage. The schedule will be negotiated from tenderers responses to the amended Stage 2 RFT. The duration and number of test and evaluation reviews will be determined by the level of MOTS compatability in the offered solutions. A schedule baseline will be established once contract negotiations have been conducted. | ||||