3.4 Progress toward Final Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

FOC

Dec 19

Dec 19

0

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Aug 07

Dec 13

Dec 19