Project Lesson | Category of Systemic Lessons |
To avoid costly and time consuming Contract Change Proposals (CCP), due to requirement variations, it is critical that Defence stakeholders provide clarity in terms of the OCD and FPS. | Requirements Management |
The time required to negotiate contracts for the Overlander project is a significant driver of the schedule. | Contract Management Requirements Management |
When the organisation is under pressure to compress schedule so as to hasten the delivery of capability to the war-fighter, key decisions must be taken in light of potential impact on the ability of the project to achieve this aim. | Schedule Management Resourcing |