1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Total

Project Stage:

Benchmark

8

8

8

8

9

8

8

57

Acceptance Testing

Current Project

9

8

9

8

9

6

9

58

Explanation

Schedule: In Service Date achieved in December 2004 with remainder of schedule well understood.

Requirement: Integration and testing has verified achievement of the majority the endorsed requirements. Operational Test and Evaluation has validated delivery of a deployable troop capability through the granting of Operational Capability 1 by the Chief of Army.

Commercial: Contractor performance is unsatisfactory and improvement is required in order to ensure critical milestone achievement.

Operations and Support: ARH System elements have commenced transition to In-Service Managers.

Project Stage:

Total Benchmark Score

Total Current Score

Acceptance Testing

57

58

2008-09 DMO MPR Status - - - - -

2009-10 DMO MPR Status - - - - -