| Maturity Score | Attributes |
| |||||||
| Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | Total | ||
| Project Stage for the confederated Phase 2 program. System Integration & Test | Benchmark | 7 | 8 | 8 | 8 | 8 | 8 | 8 | 55 |
| Current Project | 8 | 7 | 8 | 7 | 8 | 8 | 8 | 54 | |
| Explanation | • Schedule: Ahead of schedule for benchmark stage. • Costs: Major Acquisition contracts are almost finalized in line with iterative contracting strategy. In Service Support contracts are still in development. HACTS funding estimates for finalisation activities are undergoing refinement. • Technical Understanding: Support aspects are understood, however only partial capability in service. The US Navy is continuing to assist in the resolution of discrepancies discovered during Acceptance testing for HACTS. | ||||||||
| Project Stage: | Total Benchmark Score | Total Current Score | |
| System Integration & Test | 55 | 54 | |
|
| |||