Item | Original Planned | Achieved/ Forecast | Variance (Months) | Variance Explanations/ Implications |
Phase 2.1 IOC | N/A | N/A | N/A | N/A |
Phase 2.2 IOC | Apr 07 | Apr 07 | 0 | N/A |
Phase 2.3 IOC | Nov 09 | Aug 10 | 9 | Delays due to the development and service release of the Australian built software and certification issues with the countermeasures dispensers. |
Jun 06 | Jul 06 | 1 | Delays in the development and issue of Site Acceptance Report. |