3.3  Progress toward Initial Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

Phase 2.1 IOC

N/A

N/A

N/A

N/A

Phase 2.2 IOC

Apr 07

Apr 07

0

N/A

Phase 2.3 IOC

Nov 09

Aug 10

9

Delays due to the development and service release of the Australian built software and certification issues with the countermeasures dispensers.

HACTS IOC

Jun 06

Jul 06

1

Delays in the development and issue of Site Acceptance Report.