Item | Original Planned | Achieved/ Forecast | Variance (Months) | Variance Explanations/ Implications |
Phase 2.1 FOC | N/A | N/A | N/A | N/A |
Phase 2.2 FOC | Dec 07 | Dec 07 | 0 | N/A |
Phase 2.3 FOC | Aug 11 | Nov 11 | 3 | The delivery schedule for the required number of modified aircraft currently fails to meet the FOC milestone. |
Mar07 | Mar07 | 0 | N/A |
Schedule Status as at 30 Jun 10
Approval | ||||
May 98 | Phase 2.1 IOC | N/A | Phase 2.1 FOC | N/A |
| Phase 2.2 IOC | Apr 07 | Phase 2.2 FOC | Dec 07 |
| Phase 2.3 IOC | Aug 10 | Phase 2.3 FOC | Nov 11 |
| Jul 06 | Mar 07 | ||
| ||||