2.4  In-year Budget Expenditure Variance

Estimate $m

Actual $m

Variance $m

Variance Factor

Explanation

 

 

 

FMS

The underachievement is due to slippage of milestone payments and approval of Contract Change Proposals (CCPs), and associated payments, and savings from lower than expected costs for reimbursement to Air Force for tanker lease costs.

(26.1)

Overseas Industry

 

Local Industry

 

Brought Forward

 

Cost Savings

9.2

FOREX Variation

 

Commonwealth Delays

194.7

177.8

(16.9)

Total Variance