Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | MRTT Aircraft | Aug 08 | Dec 08 | Jun 10 | 22 |
Simulation Devices | Feb 09 | Dec 09 | Dec 10 | 22 | |
Acceptance | MRTT Aircraft | Dec 08 | Oct 10 | Oct 10 | 22 |
Simulation Devices and Simulation Devices Facility | May 09 | Dec 11 | Dec 11 | 31 | |
Full Mission Simulator Final Accreditation | Feb 10 | May 12 | May 12 | 27 | |
Variance Explanations | System Integration Test & Evaluation is ongoing for the first-of-type MRTT Aircraft. Originally planned as a single-phase activity, the test program was split into two phases to accommodate changes to the Remote Aerial Refuelling Operator console (as described above). The first phase, for civil certification of the modified aircraft, was successfully completed in February 2008. The second phase, for military certification and qualification of the modified aircraft commenced end of December 2008, approximately six months late due to the combination of delays to the first and second conversion phases. In particular, a further slip of 4 months to the MRTT aircraft acceptance milestone has been as a result of unexpected and continued delays in the development and certification ground and flight testing program. Acceptance Test & Evaluation of the first MRTT Aircraft will be conducted as part of the Customer Acceptance Process following completion of all system integration testing and aircraft preparation for delivery. Delays to completion of the MRTT Aircraft test process has a knock-on impact to completion of testing of the Simulation Devices as the data required for its final accreditation is dependent on a targeted flight test phase conducted at the end of the formal test program. | ||||