3.3  Progress toward Initial Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

MRTT

Dec 09

Jun 11

18

Delay to achievement of IOC is due to delays to the development, certification and qualification of the first-of-type aircraft. A further six month delay has been as a result of unexpected additional developmental and certification testing. Delays have required alternative arrangements for provision of aerial refuelling services to meet Air Force operational and training commitments.