1.6  Project Maturity Score and Benchmark

Maturity Score

Attributes

 

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Total

Project Stage:

Acceptance Into Service

Benchmark

9

10

10

10

10

9

9

67

Current Project

10

9

10

10

10

9

9

67

Explanation

  Schedule: Project activities have been achieved on schedule. Remaining MAA activities are progressing on or ahead of schedule.

  Cost: Year-end variance is primarily associated with the procurement of C-17 aircraft products being reprogrammed to comply with US Government FMS case mandatory requirements.

 

Project Stage:

Total Benchmark Score

Total Current Score

Acceptance into Service

67

67

2008-09 DMO MPR Status - - - - -

2009-10 DMO MPR Status - - - - -