Estimate $m |
Actual $m |
Variance $m |
Variance Factor |
Explanation |
|
|
|
|
The projects in-year expenditure is substantially lower than previous years and lower than forecast at project outset due to delivery of C-17 aircraft ahead of contracted schedule and at lower-than-anticipated prices. The variance of - $2.6m is primarily attributable to lower than anticipated project procurement and operating costs. |
|
|
|
Overseas Industry |
|||
|
|
Local Industry |
|||
|
|
Brought Forward |
|||
|
|
Cost Savings |
|||
|
|
FOREX Variation |
|||
|
(2.6) |
Commonwealth Delays |
|||
|
8.1 |
5.5 |
(2.6) |
Total Variance |