|
Maturity Score |
Attributes |
Total |
|||||||
|
Schedule |
Cost |
Requirement |
Technical Understanding |
Technical Difficulty |
Commercial |
Operations and Support |
|||
|
Project Stage: |
Benchmark |
9 |
10 |
10 |
10 |
10 |
9 |
9 |
67 |
|
Current Project |
9 |
8 |
9 |
9 |
9 |
10 |
9 |
63 |
|
|
Service Release |
Explanation |
The project Contract Final Acceptance milestone was substantially met in June 2010 although the project maturity score only reflects Acceptance into Service. The variance in the maturity score is attributed to the Navy decision and timing of formal Naval Operational Test and Evaluation of the delivered FFG capabilities. A period in which the operational effectiveness, suitability and the attendant levels of risk associated with operating the ships in a wide variety of roles will be defined. |
|||||||
|
Project Stage |
Total Benchmark Score |
Total Current Score |
|
|
Service Release |
67 |
63 |
|
|
|
|||
|
2008-09 DMO MRP Status - - - - - |
|||