3.1  Design Review Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Requirements

Completion of all Software Specification Reviews

Aug 00

Aug 00

May 01

9

Preliminary Design

Completion of all Preliminary Design Reviews

Oct 00

Oct 00

May 01

7

Critical Design

Completion of all Critical Design Reviews (Critical)

Apr 01

Nov 06

Apr 07

72

Variance Explanations

Software development and design was delayed due to Australian Defence Industry (now Thales Australia) repatriating the Combat System Design Authority role from Lockheed Martin in early 2001 and implementing the Australian Distributed Architecture Combat System. Thales then elected, as allowed by the Prime Contract, to deliver the contracted capability in three software baselines for technical risk mitigation.

Critical Design Review to Baseline Build 2 software completed in December 2006. Critical Design Review for Baseline Build 3 software completed in April 2007.