3.4  Progress toward Final Operational Capability

Item

Original Planned

Achieved/Forecast

Variance (Months)

Variance Explanations/ Implications

HMAS
Sydney

Jul 04

Jan 11

84

Chief of Navy endorsed the FFGs for IOR in January 2010 with limitations addressed in Table 3.3.

Final Operational Capability will be informed by the conduct of Naval Operational Test and Evaluation managed by Navy, with the allocated period now extended to June 2011 (with endorsement by Chief of Navy anticipated in July 2011) to align with the availability of the required test assets and facilities at the Pacific Missile Range Facility (PMRF) in Hawaii. Navy has identified a period in June 2011 for Anti Ship Missile Defence (ASMD) Operational Evaluation firings in conjunction with Project SEA 1390 Ph4 B and the SM-2 Stage 2 (Mid-Course Guidance) Acceptance Test Firings to be conducted by the DMO in Hawaii. The acquisition and installation requirement for an underwater active decoy system was initiated to satisfy operational preparedness requirements but with due regard to the remaining service life of the ships of the class.

All agencies continue to work closely and cooperatively to achieve the remaining operational release targets.

HMAS
Melbourne

Dec 04

Jan 11

79

HMAS
Darwin

Jun 05

Jan 11

73

HMAS
Newcastle

Dec 05

Jan 11

67

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Jun 99

Jan 10

Jul 11