Item |
Original Planned |
Achieved/Forecast |
Variance (Months) |
Variance Explanations/ Implications |
|
HMAS |
Jul 04 |
Jan 11 |
84 |
Chief of Navy endorsed the FFGs for IOR in January 2010 with limitations addressed in Table 3.3. Final Operational Capability will be informed by the conduct of Naval Operational Test and Evaluation managed by Navy, with the allocated period now extended to June 2011 (with endorsement by Chief of Navy anticipated in July 2011) to align with the availability of the required test assets and facilities at the Pacific Missile Range Facility (PMRF) in Hawaii. Navy has identified a period in June 2011 for Anti Ship Missile Defence (ASMD) Operational Evaluation firings in conjunction with Project SEA 1390 Ph4 B and the SM-2 Stage 2 (Mid-Course Guidance) Acceptance Test Firings to be conducted by the DMO in Hawaii. The acquisition and installation requirement for an underwater active decoy system was initiated to satisfy operational preparedness requirements but with due regard to the remaining service life of the ships of the class. All agencies continue to work closely and cooperatively to achieve the remaining operational release targets. |
|
HMAS |
Dec 04 |
Jan 11 |
79 |
|
|
HMAS |
Jun 05 |
Jan 11 |
73 |
|
|
HMAS |
Dec 05 |
Jan 11 |
67 |
Schedule Status as at 30 Jun 10
|
Approval |
||
|
Jun 99 |
Jan 10 |
Jul 11 |
|
|
||