Identified Risk (risk identified by standard project risk management processes) | |
Description | Remedial Action |
There is a chance that FFG capability support will be affected by an inability to establish effective software support and configuration management arrangements for upgraded systems software leading to an impact on supportability and performance. | Now no longer a Major Risk. |
There is a chance that FFG Upgraded systems will be affected by inadequate/deficient Reliability Availability and Maintainability (RAM) data leading to an impact on supportability and performance. | Now no longer a Major Risk. |
There is a chance that Operational Support will be affected by a sub-optimal Warfare Systems Support Centre facility configuration leading to an impact on supportability and performance. | Now no longer a Major Risk. |
Emergent Risks (risk not previously identified but has emerged during 2009-10) | |
Description | Remedial Action |
Nil | Nil |