| Maturity Score | Attributes | Total | |||||||
| Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | |||
| Project Stage: Acceptance into Service | Benchmark | 9 | 10 | 10 | 10 | 10 | 9 | 9 | 67 |
| Current Project | 10 | 9 | 10 | 10 | 10 | 8 | 10 | 67 | |
| Explanation | • Schedule: Project is ahead of schedule for benchmark stage. • Cost: Cost risk retired, higher score cannot be achieved until project closure is completed. • Commercial: Contractor is delivering as scheduled and contracted. • Operations and Support: Operating system not applicable to this refurbishment project. | ||||||||
| Project Stage | Total Benchmark Score | Total Current Score | |
| Acceptance into Service | 67 | 67 | |
|
| |||