1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage:

Acceptance into Service

Benchmark

9

10

10

10

10

9

9

67

Current Project

10

9

10

10

10

8

10

67

Explanation

Schedule: Project is ahead of schedule for benchmark stage.

Cost: Cost risk retired, higher score cannot be achieved until project closure is completed.

Commercial: Contractor is delivering as scheduled and contracted.

Operations and Support: Operating system not applicable to this refurbishment project.

Project Stage

Total Benchmark Score

Total Current Score

Acceptance into Service

67

67

2008-09 DMO MRP Status - - - - -

2009-10 DMO MPR Status - - - - -