3.1  Design Review Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Requirements

SRP1D Modifications

Apr 03

N/A

Apr 03

0

SRP2 Modifications

Jun 03

N/A

Mar 04

9(1)

Preliminary Design

SRP1D Modifications

Jan 04

N/A

Jan 04

0

SRP2 Modifications

Feb 05

N/A

Feb 05

0

Critical Design

SRP1D Modifications

Jul 04

N/A

Dec 04

5

SRP2 Modifications

Oct 05

N/A

Oct 05

0

Variance Explanations

Note(1):  the first version was delivered in June 2003, however was rejected in February 2004 due to administrative delays in defining the SRP2 scope.