Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanations/ Implications |
N/A | N/A | N/A | Refer to Table 1.2 Project Uniqueness |
Schedule Status as at 30 Jun 10
Approval | ||
Oct 03 | N/A | N/A |
This project does not introduce any new capability to the Hornet aircraft fleet. It is a large structural modification program designed to ensure the structural fatigue life of the fleet is sufficient to meet the Planned Withdrawal Date. Therefore, the project does not have an Initial Operational Capability or Final Operational Capability. | ||