Identified Risk (risk identified by standard project risk management processes) | ||
Description | Remedial Action | |
Long-term Hornet aircraft availability may be affected by Ageing Aircraft issues, leading to an impact on performance. | Develop a business case to detail requirements of a further structural refurbishment program to address Ageing Aircraft issues. | |
Project Office output schedule, cost and performance adversely affected by loss of critical staff (see Note). | Develop Project staff transition plan for input into TFSPO staff transition plan. | |
Note: This risk was recorded in Project risk logs as at 30 June 2009 but was not included in the 2008-09 Major Projects Report. | ||
Emergent Risks (risk not previously identified but has emerged during 2009-10) | ||
Description | Remedial Action | |
Inner Wing Aft Closure Rib modification will not achieve full life impacting long-term aircraft availability. | Procure Inner Wings to maintain availability should damage at modification location render Inner Wings unserviceable. | |