4.2  Major Project Issues

Description

Remedial Action

Lack of Maintenance Managed Items needed during the rebuild of modified aircraft has led to an impact on schedule, cost, and performance.

Renegotiate Maintenance Managed Items critical need dates with installation contractor. Negotiate Maintenance Managed Items provision with Item Managers. Cannibalise Maintenance Managed Items from other aircraft in work.