2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

Nov 98

Original Approved

295.0

295.0

Jul 07

Real Variation - Scope

154.8

154.8

1

Aug 04

Real Variation - Scope

360.6

360.6

2

515.4

515.4

Jun 10

Price Indexation

118.9

Jun 10

Exchange Variation

(3.1)

Jun 10

Total Budget

810.4

926.2