| Contractor | Signature date | Price at signature (base) $m | Quantities at signature | Price at 30 Jun 10 (base) $m | Quantities at Jun 10 | Equipment | Notes | |
| Thales Australia | Jun 99 | 170.0 | 370 | 619.5 | 737 | Bushmaster Protected Mobility Vehicles | 4 | |
| Thales Australia (SOTASip) | Feb 09 | 35.8 | 737 | 35.8 | 737 | Communication System |
| |
| Major equipment received and quantities to 30 Jun 10 | ||||||||
| Total of 300 vehicles acquired in Production Period 1. Total of 144 vehicles acquired in Production Period 2. Currently 136 from a total of 293 vehicles have been acquired in Production Period 3. Engineering and maintenance arrangements established. | ||||||||
| Notes | ||||||||
| Note 1: | Additional Protected Mobility Vehicles for Enhanced Land Force requirements. | |||||||
| Note 2: | Additional Protected Mobility Vehicles for Overlander requirements. | |||||||
| Note 3: | Other expenditure comprises: ILS deliverables, facilities, PSPs, project management and operating expenses. The major ILS deliverables this FY were Automatic Fire Suppression Kits ($4.534m), Power packs ($2.438m) and Upper Control Arms ($2.330m) all from Thales Australia. | |||||||
| Note 4: | The date of the original tender and therefore the base dollar date of the original contract was Oct 95. | |||||||