3.4 Progress toward Final Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

FOC - PP1

Oct 07

Nov 10

37

Delays in the acquisition and installation of communications harness equipment (SOTASip) have resulted in revised FOC dates for PP1 (Ambulance Variant only) and PP2, as vehicles are to be retrofitted before issue to Army.

FOC - PP2

Apr 09

Nov 10

19

FOC - PP3

Apr 12

Apr 12

0

N/A

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Nov 98

Oct 11

Apr 12