1.6 Project Maturity Score and Benchmark

Attributes

Maturity Score

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Total

Project Stage:

Benchmark

7

8

8

8

8

8

8

55

System Integration and Test

Current Project

6

9

10

8

8

8

6

55

Explanation

Schedule: The difference is a result of delays specifically associated with the Certification and subsequent FOC for Interim Anchoring Capability - now scheduled for Q4 2010.

Cost: The main cost component of the project, the WGS 6 satellite, is more than half complete and is forecast to be produced under budget.

Requirement: Three satellites are in orbit and two are being used operationally providing a known understanding of the capability to be provided by the constellation.

Operations and Support: Interim Anchoring will enter service and provide operational capability later than expected.

Project Stage

Total Benchmark Score

Total current Score

System Integration and Test

55

55

2009-10 DMO MPR Status - - - - -