Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
US Government Acceptance | Nov 13 |
| Nov 13 |
| |
Test Readiness Review | Jul 09 |
| Mar 10 | 8 | |
Jul 09 |
| Mar 10 | 8 | ||
Acceptance | IAS - East Acceptance | Sep 09 |
| Aug 10 | 11 |
IAS - West Acceptance | Sep 09 |
| Sep 10 | 12 | |
Variance Explanations | Test Readiness Review (TRR) and Acceptance milestones for the Interim Anchoring System (IAS) have slipped primarily due to the more extensive and demanding level of engineering process and breadth of WGS certification testing required to approve the system to be used on the WGS constellation. | ||||