Identified Risk (risk identified by standard project risk management processes) | |
Description | Remedial Action |
Activation of Satellite orbital slots | In principle agreement with the US Government has been achieved to enact a strategy based on a project developed activation paper. |
Obtaining US Government Security Accreditation of the Situational Awareness Tool integration may be more onerous than originally envisaged. | US Government to report on its determination via a formal security assessment, which will impact the architecture of the planning and monitoring environment for Australia. |
There is a risk that the remote monitoring and control system is not available in time to launch the WGS satellite into its orbital slot. | Participate in design reviews and highlight through Program Status Review importance of milestone. |
Emergent Risks (risk not previously identified but has emerged during 2009-10) | |
Description | Remedial Action |
Nil | Nil |