Test and Evaluation | Major System/Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | Final System (Fixed Network) | Sep 03 |
| May 08 | 56 |
Acceptance | Core System | Mar 01 |
| Jun 04 | 39 |
DMO Acceptance - Core System | Nov 01 |
| Oct 04 | 35 | |
Final System (Fixed Network) | Feb 04 |
| Apr 10 | 74 | |
DMO Acceptance - Final System | May 04 |
| Apr 10 | 71 | |
Generic Mobiles | Dec 03 |
| Dec 09 | 72 | |
Variance Explanations | Core System: Contractor delays with software development and system instability. Final Systems and Mobiles: Contractor delays with software development, resource shortages and technical reviews. | ||||