Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanations/ Implications |
IOC - Core System | Nov 01 | Nov 04 | 36 | Delays due to Contractor delays with software development and system instability. Core System supported operations until IOC of Final System. No formal Operational Release, leading to FOC, was conducted on the Core System. |
IOC - Final System | May 04 | Oct 09 | 65 | Contractor delays with software development and system instability. Deferral of operational capability. |