1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage: Acceptance Into Service

Benchmark

9

10

10

10

10

9

9

67

Current Project

10

9

10

10

9

8

9

65

Explanation

Schedule: The platform is in service and is meeting all operational commitments.

Cost: Not all project costs have been determined and the project is not closed financially.

Technical Difficulty: The capability has been released for operational use but FOC has not yet been achieved and some elements of contract delivery remain outstanding.

Commercial: Some contracted requirements against acquisition contract remain outstanding and performance against the MAA and MSA is broadly satisfactory.

Project Stage

Total Benchmark Score

Total Current Score

Acceptance Into Service

67

65

2008-09 DMO MPR Status - - - - -

2009-10 DMO MPR Status - - - - -