| Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/Forecast | Variance (Months) |
| Acceptance | ACPB 01 | May 05 |
| Jun 05 | 1 |
| ACPB 02 | Oct 05 |
| Nov 05 | 1 | |
| ACPB 03 | Nov 05 |
| Dec 05 | 1 | |
| ACPB 04 | Mar 06 |
| Apr 06 | 1 | |
| ACPB 05 | Mar 06 |
| Apr 06 | 1 | |
| ACPB 06 | Jun 06 |
| Jun 06 | 0 | |
| ACPB 07 | Jul 06 |
| Jul 06 | 0 | |
| ACPB 08 | Oct 06 |
| Oct 06 | 0 | |
| ACPB 09 | Nov 06 |
| Nov 06 | 0 | |
| ACPB 10 | Mar 07 |
| Apr 07 | 1 | |
| ACPB 11 | Mar 07 |
| May 07 | 2 | |
| ACPB 12 | Jun 07 |
| Jul 07 | 1 | |
| ACPB 13 | Sep 07 |
| Sep 07 | 0 | |
| ACPB 14 | Nov 07 |
| Nov 07 | 0 | |
| Variance Explanations | Boats 1-5 delayed due to contractor labour shortages - permissible delays. Boat 10-12 delayed due to configuration changes and change to delivery location -permissible delays, plus defect rectifications by the contractor. | ||||