1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and

Support

Total

Project Stage: System Integration and Test

Benchmark

8

7

8

8

8

8

8

55

Current Project

7

8

8

8

8

8

8

55

Explanation

Schedule: There have been minor schedule delays associated with the update to the new acquisition strategy being reflected in the contracts with the phased array radar. All contracts are now in place, but will require completion of the lead ship (May 2011) test activities before the benchmark score can be assessed as achieved.

Cost: With the approval of the new acquisition strategy (single ship installation only and test before further ships approved) the costs remain within the approved budget.

Project Stage

Total Benchmark Score

Total Current Score

System Integration and Test

55

55

2009-10 DMO MPR Status -------------